Coal linkage, funding woes delay UP’s 3,200 mw power expansion

Published on: June 18, 2026, 5:30 a.m. | Source: Hindustan Times

“The biggest bottleneck is coal linkage. The coal source that Coal India Ltd has offered is expensive. We want the rearrangement of coal allocation from a cheaper source,” says UPRVUNL director